for the connection project,
the first delivery was started from 19 Oct and
completed at the end of Oct. 2003.
Government made every effort in order to proceed
the construction in a proper way by visiting the
site and supporting techniques over 17 times since
March 2003. It is estimated that the materials
and equipments provided contribute to favorable
progress of the construction.
South and North Korea conferred about practical
affairs needed for construction each other since
a ground-braking ceremony, so that a temporary
highway of the Donghae line was opened on 11 Feb.
2003 and it has Mt. Geumgang sightseeing by land
conducted.
Especially, it was agreed that South and North
Korea Railroad Connection Event would be conducted
in the 5th South and North Korea Economy Cooperation
Committee held in May 2003. Finally, the connection
of the Gyeongui and Donghae line was completed
on 14 June 2003, which was separated for half
a century.
Although a train has not run yet, it accelerated
the connection construction to complete. |